May I interrupt a little, after reviewing all your requirement…..
1. The shipment no 21 which is plan to load 31/3, we have checked the production and there are no available machine to produce additionally of item 1.5L Green for 150 cartons to catch up the schedule of 31/3 loading.
2. From point 1, the only way we can do is to take 150 cartons of 1.5L Green from your April forcast (Original 1000 cartons) arrange loading for you with this shipment no. 21 instead.
3. For the closure below : Please advise you want to load it in which shipment no……..