The WHE Evaporator is now up and running very well after a few weeks of testing and tuning the system.
We believe that the evaporator is now tuned and ready to hand over to you for regular production.
But the monitoring and training of operators will continue until November 19th.
In order for you to take over the evaporator and start normal production, we will need you to sign a “Take over certificate”.
This means that you acknowledge that the system complies with contract no. 4000505-141016 in all aspects.
We are very satisfied with the performance of the WHE Evaporator, and we hope you are well satisfied too.
I will travel to Thailand next week and expect to be in SEAPAC site one of the days in next week.
So I hope we are able to have a short meeting together to conclude the WHE Evaporator part of this project.
Let me know if this is possible for you and which day fits your schedule best.
Have a nice day! Kob Khun Krap!
PS.
Take note that this is only regarding the WHE Evaporator, and not the RTO part.
RTO tuning is expected to finish soon after the ducting transition work has completed.