Dear Sirs,
For this alerts, I’d like to project site to inform the purchasing department of scope of our work was delayed.
And for now we also modify the alignment and extra strength to runway beam I will go re-check again on 13-Nov-15.
For the span that I'll cut stage of girder needed to complete alignment before.
And span period cut and color girder estimate 2 weeks after value of span complete.
From schedule I will install runway rail and installation crane on 1-4 Dec 15 .
In order to prevent mistakes for overdue occurs and information for purchasing and project site.
Please inform this information to the purchasing department of your.
BR
Pongpan Arunwat