pls. consider about date of stop crushing stop boiler for connect cable prepare export line 2.
this date in schedule can change up to the end of crushing
Note
1. Transformer arrive on the end of Feb'16, and k. soyti inform need cane 120 ton for installed
2. schedule can change up to boss.