Since Potonggang will cast concrete on Tuesday 16th of August, Monday 15th of August is DPRK national Holiday. The Contractor have not send me request for casting concrete, and since the amount of concrete to cast is about 380 m3, the sequence of casting therefore is very important, I have asked for sequence of concreting in writting accompany by drawing whether they are going from front to back or back to front.
Yesterday in the meeting we have talk about curing which they have satisfy me, but the method of compaction when backfill did not.
I will wait for their satisfactory reply before I approved these footings for casting.