Thanks Hervé,
A few comments on the minutes :
- QC documentations (especially Petrovsky and FRC): needs to be in completed always in time for shipment; see current holding of Petrovsky shipment due to QC certificate not available (pending raw material cert from SCG).
- Comments on master batch from Bruno Peter: Please review with me in detail as I do not understand what we are trying to do here; colour measurements for example have to be done by VSL on finished pipe samples and not on masterbatch (this is how it was done for our 7 standard colours) unless I misunderstand something
- Timing of raw material testing; it is clear that we need to improve here in order to ensure that all received material is compliant and fully documented before running into urgencies in case of rejection of some material
Best regards,
Andreas