Please be inform that we will have a meeting by 1pm to 2pm to discuss the following
- Fabrication Status
1. How many TON we complete for this week
2. Priority item need to Finished
3. Set Target Schedule for Sub-Contractors
- Painting / HDG
1. Priority Items need to Follow-up V-Tech
2. Painting Material update
3. V-tech must be monitored for the Priority to paint first
- Material /Purchase
1. Need update for Materials for the Project if Enough for Fabrication.
2. Need Bolt update in preparation for Pre assembly.
- QC
1. Inspection Report
2. Data Base
3. Inspection with HTC with JBE for Final Inspection before send to site.
- Transportation
1. Delivery plan for the first Platform
2. Available HIAB and TRAILER