Sorry for late reply. I was just finished meeting with supplier and Watcharapong.
1. The AC controller will be done in CW18 ( next week). Now the status of installation the BAS system is around 80%. Next week they'll join all air condition to BAS system controller and run the testing.
2. The spriger inside UPS room can't bline or remove in this time, becuase the springer systems is ready, water is in inside the pipe. We're discussed with TICON. they need to plan to do on next time PM. In that time
They'll come and inform us agian.
3. CW24-25 we will work fully week. No holiday.
4. I sent you the pictures of 3 rooms are look like now. \srvray03group$DTSDTS9IT_DeptOpen_TopicPictures