First of all, we would like to clarify the 3rd V. O. claim is RM23K or RM211K?
Besides, the following are some of the points highlighted by Peter –Zenworks during our today meeting:
The awarded given to Zen-works for fabrication is worth RM157K based on 40 MT of material (based on KPD quotation).
Durr would not accept additional claim on this V.O. was the risk of execution shall be responsibility of the contractor not the employer.
As represented by Peter from Zen-works, Zenworks had incurred more than RM157K for its costing due to the following reasons:
1) Drawing initially given was not accurate and amended after start fabrication; and
2) Drawing was given on a piece meal basis, which causing ineffective execution.
We have requested Peter from Zen-work to furnish his supporting document for the local fabrication and facility costs.
For this V.O., you shall discuss this matter with Zen-works for an amicable solution.
If you have any doubt on this 3rd V.O. claim please contact Peter of Zen-works for clarification.