Dear Khun Lucio / Khun Preecha and all,
Thanks for the shop drawings, we will issue the revised PMI as attached for your record.
In future, please note the following HHT standard procedure:
1) The site team can order work to the contractor by PMI but shall not agree the cost of VO with the contractor.
2) All PMI regarding additional work is draft by site and approved by head office, then issue to the contractor.
3) The site team shall not in prior agree any cost of VO with the contractor without the knowledge of the head office.
4) Head office QS will coordinate with the contractor for quotation of VO, assessment and confirmation of the cost of VO.
5) The confirmed VO cost will be notified to the contractor by APMI.