egarding this between PJC and IPM first before I answer Gary….
1. We have the sliding door fitting for master bedroom arrive 15/12/2014. So if we can work that week and finish by 20/12 with your team as you need to do wood panelling over the sliding door once fitted in this room.
2. We could have fabric bed head panels install this week also?
So PJC out of all rooms by 15 /12 so we can finish and clean also, except items 1 where we work together, can you?
Also Gary wants timber bed frame overlay our plywood bases, same as wall panelling, can you do for us and we pay you direct?
Regards
Brianna