Jean-Marie,
The main problem is that the IRPC laboratory doesn’t provide the testing reports according to the agreed dates (see attached for your reference the pending testing reports). As a consequence, some of the stay pipes have been produced and shipped without testing report.
We will organize a meeting this week with people from IRPC laboratory (e.g. Mr. Karn) to see how we can speed up the process.
Regards,
H.Maniez