23. Given that there is less than six months to go and the construction of the biogas power plant is at 30% completion stage, is there any problem for PPO2 to get its crushing mill and biogas power plant ready for operation in July 2016 as assumed in the credit memo? Won’t PPO2 need to carry out trial runs for its crushing mill and biogas power plant before it starts operation in July 2016?