We will start filling water into pack no.21 within on 31 May 16 and to propose start static test after that if possible. (RT remaining only 1 joint must be completed within tonight) : Today RT only one joint already cleared and flushing test is done, also right now we under preparing filling water for static test start on morning tomorrow and will be completed within 3 May 16 tomorrow krub.
Ø we have plan to handover each of area at below lower deck zone start on 2 may 16. Postponed to be 3 may 16 due to static test for open drain package (pack no.21) will be completed on that day also krub.
Scaffolding dismantle work each of area will be updated and decided by daily basis from Kh.Somsak