All,
QC team has flagged up another key concern raised that actual packing stations are also not matched with label on some stations.
This is because the workload is changed on some stations to avoid walking across CKD line but taking bags from same area from skid
It is practically right however any process change has been made shall be matched with printed label for traceability.
PE will has to correct all picking and packing information to be in line with station or man changes which required approx. 7 working days
Due to capacity limitation to allow a full week , We agree with PE to make changes on annual stock take week25 which will make us ready to properly implement the 16BPD pattern from mid of week27 (July 1st ) onward.
Production will keep building kits with 24 BPD pattern and utilise the planned down times approx.. 1-2 days a week on practising 16 BPD on trial kits only ,PE will arrange the trial build cards for production.
Any concern please let me know
Thank you,