Dear Khun Witchara
I have arranged a surveyor to mark out Fences at Block valve 7 and 8.
Panel mounting frames for Block Valves 2, 3, 4 and 5 have been delivered to the GDF.
You have some cable ladder. More is to be delivered to you this week.
So I believe that the work fronts that you now have available to you are as follows.
Pick up Panel mounting frames from GDF and install in BV4.2, BV4.3 BV4.4 and BV4.5. Please coordinate with Khun Chinnachot.
Install cable ladder in BV4.4 and BV4.5. Then as more ladder is delivered move on to BV4.3 then BV4.2.
Trenching and earthing at BV4.6. Install earth rods and earth cable BV4.6
Arrange sand for BV4.6.
Install lighting cable at BV4.6.
Arrange cable tiles for BV4.6.
Mark out trenches at BV4.7 and BV4.8. Then as we finish trenching at BV4.6 we will move the excavator to BV4.7
Mark cable drums at McD Fab yard and if we have the correct cable delivered for lighting take to BV4.6
Mark out more trenching at BV4.6
Please advise what work fronts you will commence this week.
Regards and best wishes
Charles