The Master Schedule is developed in a logic linked bar-chart format and highlights overall durations and major project milestones. This schedule remains unaltered during the life of the project; unless any COMPANY approved scope changes occur which significantly affect the logic and/or the timescale of the schedule. The schedule is updated from the more detailed schedules on a monthly basis, indicating actual status and forecast completion at cut-off date.