Dear Creful Team,
The issue with MEP is a coordination issue between contractor, Allied Metals, Jujak and Creful. Myself and Craig requested all contractors to ensure coordination was complete and nothing was missed, unfortunately through a lack of supervision the mistakes were made and now the schedule for completion has been jeopardised.
I don't expect to have my team onsite 24 hrs a day monitoring works to ensure instructions are being followed, this issue could have been prevented through supervision from Creful.
I am extremely disappointed, but lets move forward and make up for the lost time, please ensure supervision is improved and I need all wet works complete by Tuesday 12th August with out fail.
Please let me know what assistance Craig and I can be, but lets not fail on this deadline.