Use Work Order Routing Maintenance (16.13.13) to add, delete, or change the routing of a work order that is exploded, allocated, or released.
In general, the start and stop dates for work order operations are not frozen. The system automatically reschedules the operations from the due date in any of the following situations:
• A work order is processed in Work Order Maintenance (16.1) and the initial status is Batch, Planned, or Firm Planned.
• A work order is processed using Work Order Maintenance and the final status is Firm Planned.
• A work order’s due date changes.
• A work order is replanned by CRP.
Note: If you are using the Advanced Repetitive module, you cannot add a routing operation to a cumulative order using Work Order Routing Maintenance. Instead, you must change the routing and roll up the cost again. See Advanced Repetitive