2.12 MATERIALS
2.12.1 Company Issued Materials
2.12.1.1 Company will issue all materials on a Work Package basis, as per Appendix I: Part 9 – Detailed Scope of Work and Provisions. It is the responsibility of Contractor to collect, properly store and tag, prevent material damage, maintain traceability and issue to the correct field location for installation.
2.12.1.2 All Company issued materials remain the property of the Company and any surplus materials remaining with the Contractor shall be returned with material return voucher prior to contract completion.
2.12.1.3 When Services include the welding of piping materials, Contractor shall co-ordinate all material inspection activities with Company Inspection department.