However, as agreed before between MC/TJEL/NWRT, TJEL can proceed with the packer plates installation at CW Pipe Section 6 even if NWRT has not yet handed-over officially. NWRT has to consider also the actual condition in the site whereas our main purpose is to expedite the works in order to cope up with the schedule that’s why an agreement has been made to proceed with TJEL works in advance.
On the other hand, NWRT as a professional contractor, has to take extra care of any installed or existing structure during the execution of their work in order to avoid any damage on the structure(s).
Your kind understanding on the above matter is highly appreciated.