FYI, please help to defend in case BTS-account ark about big-item claim as below information.
(Maybe have a problem in BTS payment to HHT for end of this month /that I don't sure.)
- Provisional sum item for lanscape work (19.1 mb in original contract) without any detail & BOQ for submit to BTS.
- I already submit progress claim 75% in this part (30Sep) to "BTS" (HHT many release payment to sub-con)
- I still waiting clarify scope of work in original provisional sum 19.1mb + VO. XXXX bt. from our team for submit to BTS.
- End of October posible to submit claim nearly 100% of Original 19.1 +Additional. xxx bt
- Overall Claim last month ~ 90% of "Original Sum + APMI Approved"