I have just sat down with Beer and De, I have told both that we should not order this equipment until we have run the 2A converted unit in production, proven it works to our expectations and the product passes the metal mark test on the colours we need, I have stressed this is urgent. Currently the unit has been handed over to Kai and production, he is completing his production trials, these I understand expect to be validated within the next day or so.De and Cerinnov are now working on 3A and this has all the equipment needed, therefore at this stage only 3B requiring equipment, the lead time is only 1 week for the equipment required and so there should be no delay to the final machine conversion or maximum of 1 week.I have also challenged the team to look at all the equipment we currently have to ensure that when we order we order the minimum required, but I will go through this when needed