While the duration and cost buffers are in a descendent trend as the result of the risk events impact (table 3),
an important aspect of the risk simulation was to identify the position of the target dates relative to the position
of centroid. It resulted that in different stages of the project execution, the position of the target dates may
belongs to one or another quadrant relative to the position of centroid (Fig. 6).