1.Request to scan bar code after printed the label for verify the correct label and establish work instruction also.
2.Daily check sheet of C/B is not clear and difficult to understand.
3.Process flow chart not accordance with actual process, should be review and revise.(Process Flow : apply label before assembly ,Actual process : Apply label after assembly)
4.Submit 8D lasted revision within today (5thMay,2016