After the installation carry out the following procedure to perform leveling of the machine.
1.Loosen all level adjustment screws 3-5 so that they do not touch the floor .
2.Clean the surface for placing the level.
3.Put the levels 1 and 2 into the positions shown in the figure on the previous page.
4.Insert the leveling pads into the positions directly underneath the screws 3-6.
5.Tighten the level adjustment screws 3 4,and 5.
6.adjust the level adjustment screws until the gap between the machine and the floor becomes about 10mm.
7.Adjust the level adjustment screws 3 and 4 to make a horizontal plane with the level 2.
8.Adjust the level adjustment screw 5 to make a horizontal plane with the level 1.
9.Adjust the level adjustment screws 3, 4 and5 to make fine horizontal planes with levels 1 and 2 (Tolerance 0.02mm/m).
10.Tighten the level adjustment screw 6 with a torque of 9.8 Nm.
11.Check that all the level adjustment screws are tightened.
12.Tighten the set screws for the level adjustment screws 3-6 to fix them.