Requires that the siting be based on meeting design
basis scenarios (e.g., design spills and
impoundment fires), or
• Current version allows risk assessment
(performance-based) alternative for siting (if the
authority having jurisdiction approves)
– Prior to the 2013 version, the risk assessment
approach was in a non-mandatory Appendix E
– Now located in the standard as Chapter 15