Dear K.Sarawut and all,
I would like to update BP1 improvement master plan on 5-Nov’16. Please see details in file attached kub.
Last week plan:
1. Document control
- WI_ Customer ~ 9 issues
- WI_ Procedure ~ 2 issues
- One point ~ 16 issues
- Form BP1 ~ 21 issues
2. WI. Moriroku ~ Done , submit to MGR. review and register.
3. Gras control ~ Delay, K.Chainart please set recover plan kub.
4. Empty location control_ IKT ~ can’t improve right now.
For the delay item that who was in chart please set recover plan and action as plan.
This week plan:
1. Control plan ~ All supervisor
2. WI_ JX Nippon ~ Dejchai S.