Hi Khun Ple & Khun Fa,
Gentle remind to this mail. .
I don’t see any progress on this? Can you update where we are.
I can see that most of them are so simple and easy to complete NC.. they only took photo that you already improve from the date auditor audited?
Pls confirm they are all done, if not when you expect to complete them? As it’s about over 1 month now?
Also Technical audit NC which I heard from Khun Nat that there’s lot of NC as well.
Shall we take all those NC on table and get understand them and agreed time line?
Hi TL&t team,
Thanks to share all NC both Ethic & technical.
Br,
Pao Ruji
Direct Source Electrical