-Install the door already but have some defect they will edit tomorow again. and Will install the door Pantry cabinet and laminate sheet magnetic tomorrow, They will install the aluminum u channel logo wall and touch up all for 12/6/15, section top and glass pantry cabinet to install 19/6/15.
-D-NET Install the power outlet and lighting then some and install again tomorrow. Grid suply air and the return air is installed in this week. Parts sprinklers, emergency lighting, cctv, access control is tracking K.best for that day is installed
-KWC Cleaning tomorrow 13:00pm.
-Carpet delivery tomorrow and installation 12/6/15.