Is it OK if we will come back to you by next Monday?
A very very high level answer would be the following:
1. Whether current WHRU provides more than required duty performances, and if yes?
Yes. This gas turbine produces more exhaust heat and therefore the current WHRU will provide more than required duty performance.
2. Whether the coil bundle can be smaller, therefore weight of bundle and unit smaller too (cost as well)?
Yes. The coil, weight, size of the coil bundle and therefore cost of the WHRU will be smaller too.
3. Just provide high level estimate without spending much time on this issue.
As above.
4. Please indicate important figures that we are aware for the next phase
Please advise what are the important figure that you required?
For your information, we will start the redesign this week and should be able to provide you with a tentative size, weight and revised duty of the WHRU.
For our planning purpose, can you advise what the status of this project is? When will the project be awarded to EPC? When is the target completion of this platform?
Hope that the above is in order. Thank you.