Data Center:
1. Wiring schematic of PEA/Generator -> MDB -> Circuit Breakers (Added documentation)
2. Expand MDB details to include full explanations with parts and services included (current details were truncated due to quotation page size)
3. Expand MDB to include circuits for Data Center lighting (20 amps)
4. UPS – Split UPS into a separate quotes. Provide option. Single UPS or Two UPS. STEC may initially purchase on a single UPS this year and a second UPS next year. It is OK to delay the 2nd UPS purchase however Aware strongly recommends that 2 UPS units are used for delivering power to all systems. If a single UPS fails, then all power is lost to connected devices. (Keep all MDB circuits for the plan of 2 UPS units)
5. Security Camera system with 3 or 4 cameras and DVR with 2 weeks of full camera coverage. Does not require pan/tilt cameras. Does not require motion detection. Camera locations are not currently known. Cameras must be wired. (Power for Cameras and network wiring for cameras is the responsibility of STEC)
6. Remove all racks, fans, cable trays/management, CAT 6 cabling and shelves. (STEC will use all existing racks and relocate the racks for the cutover)
7. Keep 6 x 12 port PDUs
8. Remove access control system (STEC will use key locks for the two doors)
9. Modify Professional Services charges to accommodate changes above
10. All other details stay the same