After review on SS16 implantation planning, Sheico finish date is quite late.
In case of inspection reject, Sheico have only few days to rework on FG due to factory close during year end.
Do you have any backup plan on this situation?
** Please note that we can't postpone loading date of implantation order anymore.
It have to deliver ontime as Sheico used to confirm.
Thanks to check and rework on finish date. It should be early or around 21-24 Dec.