Because of uncertainty in duration as well as variation in
execution quality and dependency logic of activities, schedules
are bound to change as construction progresses. It may be
possible to model this uncertainty during the planning stage, as
is done by using probabilistic distributions to characterize
activity durations in the Program Evaluation and Review
Technique (PERT). However, the actual manifestation of
uncertainty is known only upon plan execution and must thus be