According to the Company First Technology Co., Ltd. is honored for the implementation of supply the material and equipment in process install. Project KidZania Bangkok within Siam Paragon 5th (Building System.) in the work install as follows.
1. Chiller Plant Room. 7th
2. Installation Ventilation System for Example Fan ventilation and Ductwork.
3. Installation Fan Coil Unit within Establishment and Room thermostat for open and close
Details of the documents referred to above
Now the Company First Technology Co., Ltd have completed all operations. If there is any damage, occur in the future still has guarantee. Material and equipment from Company First Technology Co., Ltd according to the contract is mentioned in another 18 months. Since that date you receive handover material and equipment. Therefore, request you signed the documents certify material and equipment in install lastly, attach