Regard to The project Bumrungrad Hospital (Building C) will be wiring with testing and commissioning for 22, 24 September 2016,
So we would like to request for overtimes on 22, 24 September 2016 for our testers for catch-up our schedule.
The tester names are as below:
1.Nutthaphon Singthong
2.Arnon Ketsukum
The schedule for working on 22, 24 September 2016.
Details as followed:
- 22 September 2016 (08.30 – 21.00), To do wiring terminated cable and Adjusting with Find tune parameter. ; Overtime 3 hrs.
- 24 September 2016 (08.30 – 17.30), Commissioning to fast speed elevators. ; Overtime 8 hrs.