The early identification, communication and management of change are the responsibility of all members of the project management team, Contractors and Suppliers. The management of change review process is illustrated Figure 1. Once a potential change is identified, the initiator shall advise the Project Construction Management Team via a Change Notification (CN) form (Appendix 2). The Construction Manager will then designate an MCC to complete sections 1, 2 of the CN Form and the reviewers required part in section 3. Each CN form will have a unique number.