Today,
-D-NET install fire protection already.
-Dreammackel Touch up,painting the door,logo wall and cabinet pantry already.
-Ultra screen Install roller blind that edit already.
Tomorrow,
-D-NET Install access control and will install emergency light,exit sign 27/6/15.
-Artmatrix edit defects
-Feltech edit defects eco panel.
-Delivery Teble dining area and counter bar.
-A chui will painting ceiling on monday again because gypsum is not dry.
Tomorrow P'Nhui will go to site krub.