Dear Khun Jerome
On August 26, 2016, I’m got information from F/O (K.Anuree). Khun Poon finish work about 03.30 am and go back to her room 302. She found a lot of water on corridor. So front inform engineering (K.Chao) for checking immediately and inform K.Kamon at the same time.
First, K.Chao shut down the motor pump of the building A,B. K.Kamon arrived at the hotel around 03.40 am survey and find that main water pipes have a lot of water leaking and cannot be repaired. Need to change the new E-blow one set.
But Sor Anan has no spare parts. So K.Kamon go to buy in Pak Chong and come back about 8.15 am. And engineer team/ Sor Anan/ Project Asia team they make the repairs completed in time, 11.15 am.