For Fac#6 floor 1 cleanroom process already complete but the remaining 24% are areas is not in use (waiting improvement layout)
And Fac#6 floor 2 we will install on 27 Sep’14 (Holiday) if not have production plans. (I will confirm with Planner and P’ Rajit)
For Fac#6 floor 3 The rest of the area under the machine cannot be installed (safety). Which will be installed on 20 Sep’14
Because winding HDD1 no production. (I will confirm again)
Yesterday , P’ O informed that will send list name of technicians to training kha.