All the tanks should be full or empty
> Un-necessary objects /equipment should be removed other than objects that should be containing in lightship.
> Sounding measurement of all tanks to be taken before the experiment.
> List of materials to be taken off including weight and center of gravity to be prepared after inclining experiment.
> List of materials to be installed including weight and center of gravity to be prepared after inclining experiment.
> Two U-tubes are to be fitted at car deck at frame no. 30&58 respectively at Long: BHD 5.4m O.C.L. (P&S)
> Four weight group of 8 T each to be prepared on car deck, 4.5m O.C.L., between frame no.35 & 55 , two in port side and other two in STBD side.
> Weight movement is as follows.