Dejar Charlie,
Pelase note that we are finishing the equipment as we promised before.
Please notice that 23rd is not the date of equipment ready, it is the date that the vessel leaves the port of buenos aires, that means that to catch that vessel we must enter to the port at least one week before ( February 16th). In that case we will be loading the equipment in our plant in Escobar at the end of next week (February 9th), if the forwarder confirms this requested vessel.
Please help us with this.