1.After receive mold, we will check the detail within if it has sharp. We will use sandpare Number 1,000 decrease sharp. Because if detail within not smooth when casting the clay may be rip.
2.After check mold finish. We will blow clean the mold and complementary mold.
3.Pour slip in mold and shifting swivel mold. Because chase bubble out of slip.
4.Timer afler pour slip when're punctual, drain slip off mold and upside down mold, wait clay set.
5.After the clay's set, slowly take off mold pulling mold the same direction.
6.After take off mold, weigh the clay balanced with weigh limit from factory.
7.After finish will send clay to finishing team.