Pilot-scale demonstration on a coal-fired power plant flue gas at a 1-1.5 MWe scale is currently planned under a project supported by DOE (project award DE-FE0007453). Mechanical completion of the pilot plant was achieved in July 2014 and the final commissioning activities are being completed to enable start-up of operations in late 2014. The pilot plant incorporates the capability to test a number of unique features of the Linde-BASF technology aimed at lowering the overall energy consumption as well as resulting in capital cost reduction.