Dear khun Amrish,
The Contractor contract is signed yesterday.
Term of payment is : 1. Paid 30% with deductible of 5% for warrantee. Should be paid at agreed date.
2. Paid 20%
3. Paid 20%
4. paid 15%
5. Paid 15% at complete job.
6. the warrantee of 5% will be paid after warrantee period. (later 1 year)
Renovation period is about 3 months, contract said contractor should start working process not later than 1st Oct 2016
Today they are delivery some instrument and material for scaffolding to store at space beside the gym.
There workers is starting on next Monday. And khun Samaan will provide time table tomorrow.