BCU PAT Bangyo still not complete ,still remaining BUS-Section 1 and 2 , Cap Bank 1 and 2. Then should not say in the report 100%. Now we can interface to BCU 10 bay but in the contract should be 13 bays
Then I will discuss during meeting and will inform you about remaining.