Three alternatives were considered: The current line,
ILP-Pack out combination, and ILP-FVT combination
alternative. Many criteria were used to evaluate them as
shown in the Table 12. The suggested alternatives were
better than the current one in terms of line balancing index
and unit per hour per person one. In addition, twenty five
percent of human resource were reduced; and overall labor
effectiveness index is increased in both suggested
alternatives. Currently, the option 2 has been applied due to
without investment more. However, the ILP-FVT operator
worked most full time. It is not good for a long time.
Therefore, option 1 would be invested in the near future.