As discussed today I have approved your April Claim of which a payment of around 400k will be paid next week.
Based on our discussion I need the following.
1. Marked up drawings of the panels you have installed on the Podium and Upper Podium.
2. Marked up drawings of the panels you have installed on the Tower to date...may Claim.
3. Marked up drawings of all the steel you have installed on the Podium and also the Tower.
The reason for this as explained is that the areas of facade in some parts of the building are higher than your contract value.
Also the amount of heavy steel you are installing may be over the total weight you are claiming, hence there may be a benefit to this exercise. Any way I need you to do this and submit with your May claim to me here at Ekkamai.
The drawings you can get from site if you have not got already.