Typical Work Products
1. Requirements impact assessments
2. Documented commitments to requirements and requirements
changes
Subpractices
1. Assess the impact of requirements on existing commitments.
The impact on the project participants should be evaluated when the requirements
change or at the start of a new requirement.
2. Negotiate and record commitments.
Changes to existing commitments should be negotiated before project participants
commit to the requirement or requirement change.