If the Contract specifies that the Contractor shall design any part of the Permanent
Works, then unless otherwise stated in the Particular Conditions:
(a) the Contractor shall submit to the Engineer the Contractor’s Documents for this
part in accordance with the procedures specified in the Contract;
(b) these Contractor’s Documents shall be in accordance with the Specification
and Drawings, shall be written in the language for communications defined in
Sub-Clause 1.4 [Law and Language], and shall include additional information
required by the Engineer to add to the Drawings for co-ordination of each
Party’s designs;
(c) the Contractor shall be responsible for this part and it shall, when the Works are
completed, be fit for such purposes for which the part is intended as are
specified in the Contract; and
(d) prior to the commencement of the Tests on Completion, the Contractor shall
submit to the Engineer the “as-built” documents and, if applicable, operation
and maintenance manuals in accordance with the Specification and in sufficient
detail for the Employer to operate, maintain, dismantle, reassemble, adjust and
repair this part of the Works. Such part shall not be considered to be completed
for the purposes of taking-over under Sub-Clause 10.1 [Taking Over of the
Works and Sections] until these documents and manuals have been submitted
to the Enginee